The Requirements Traceability Matrix captures all the project requirements and enables you to trace Requirements to Test Cases and Defects. You can filter and export the report.
To identify risks to Production, you can monitor the execution of the tests covering each requirement.
- From within a Project, select the Reports tab
- Click on the Requirements section to expand
- Click on the Requirements Traceability Matrix
The following information is displayed for each Cycle -
- Planned Test Coverage
The number of Test Cases Linked to the Requirement
- Pending Execution Tests
The number of Test Cases where not all Steps have been Passed
- Test Plan Execution
The number of Test Cases where all Steps have been Passed
- Completion Rate
The percentage of Test Cases where all Steps have been Passed
- Defects
The number of Defects associated with each requirement
- Coverage Risk
The current Risk Indicator
Filter
To filter the report, use the filters above the report.
Below is an example of selecting multiple Risk indicators for the Coverage Risk filter.
Export
To export the matrix to an Excel spreadsheet, click on Export
Tip!
For a visual progress dashboard per requirement - use the Requirement Progress tab.