How to mark a cycle as completed?

When a Test Cycle has been completed, select Complete Cycle under the cycle's general tab.

To do so, navigate to the "Tests" tab and select "Tree" view. Highlight the relevant cycle and then click Complete Cycle.

This will change the status of the cycle to “Completed” in the main dashboard.



At this point notifications and workflow will stop and you can move on with any additional cycles or to close the project out.